OHS Code

Published Date: July 01, 2009
Bookmark this page

Part 6 Cranes, Hoists and Lifting Devices

Section 102 Operation

An operator of a tower crane must

(a) ensure the safe movement of the crane and its load at all times,

(b) verify at the beginning of each work shift that the mast is plumb, and

(c) verify at least once in each 24 hour period that the limit devices described in section 101 are operational.